Emergency Tank Farm/Lot Expansion Project
Geography: fort mcmurray, Alberta
Industry: Oil & Gas
Materials: 40 mil LLDPE, Geotextiles, Geo-Composite, Specialty Sump Design, Penetrations, Containment Wall Attachment
Duration: 2 months
Project Description
Engineered Containment was called in by the General Contractor and Owner to complete this project as the contracted liner contractor had been asked to leave the project due to serious schedule issues. ECI coordinated a large construction team and mobilized quickly to complete the work and get project back on schedule.
The liners required delicate installations due to cover fill and tank placement.
This project consisted of detailed sumps that ECI designed, manufactured in its plant, and installed.
outcome
Key personnel led to the success of this project. The project was completed without issues and on schedule.
lessons learned
General Contractors and Owners should take additional time in qualifying Tier 1 liner contractors to assure success with these types of projects.